How Does the Program Work?
LADWP will purchase energy, for a term not exceeding 20 years, from projects via a Competitive Offer Power Purchase Agreement. Under the FiT+ Pilot Program, LADWP will use a competitive bidding process for up to 10 MW of solar + storage project within the City of Los Angeles. The 10 MWs of available capacity will be split over three bidding tranches. Each tranche will consist of a 90-calendar day window to allow for proposals to be submitted for only those eligible Zones.
FiT+ Pilot Program projects may also be designed to:
- increase the reliability and resiliency of the grid by allowing energy to be consumed on-site during a potential LADWP grid outage (Resiliency); and
- reduce customer energy consumption from the grid during certain peak periods (Peak Shaving).
Maps of the FiT+ Zones can be found at the link below. Detailed explanations of the FiT+ Zones and the associated maps can be found in Section 3.5 of the FiT+ Pilot Program Guidelines.
FiT+ Pilot Program Capacity Table |
||
---|---|---|
In-Service |
Active |
Available |
0 MW |
0 MW |
10 MW |
Updated as of 1/25/2024 |
Notice: Tranche C New Application Period begins January 29, 2024
A new competitive application/bidding period for Tranche C begins on January 29, 2024 and will end on April 28, 2024. Previously unawarded capacity will be made available for the new application period. The program will only accept applications for projects within the eligible zones. Please refer to the FiT+ Pilot Program Guidelines for eligibility requirements.
Tranche Segmentation |
|
---|---|
Category |
Tranche C |
Eligible Zones |
South LA |
Tranche Capacity |
10 MW |
The pilot program design and pricing structure will ensure that energy will be dispatched in specified zones and during targeted hours in order to reduce system-level demand. In-depth explanations of the competitive bidding process, program pricing structure, and other program details can be found in the FiT+ Pilot Program Guidelines.
How to Apply
The FiT+ Pilot Program requires completed hard copy application packages. Please download and print the FiT+ application package. Complete the application package and mail it to our LADWP office. Access to the documents can be found below.
Program Guidelines
The Feed-in Tarff Plus (FiT+) PIlot Program Guidelines provide background information and procedures for participation in LADWP’s FiT+ Pilot Program. It is strongly recommended that all applicants familiarize themselves with the FiT+ guidelines before applying to the program.
Application Package
The FiT+ program requires hard copy application packages. Please download and print the FiT+ program application package.
Contract Documents
LADWP will purchase energy from eligible projects under a twenty (20) year Competitive Offer Power Purchase Agreement. Applicants must also submit an Interconnection Agreement along with Supplier Contract Data and Business Compliance Forms for contract execution.
Please mail the completed application package and documents to:
LADWP Feed-in Tariff Program
ATTN: FiT+
111 N. Hope St, Room L-43
Los Angeles, CA 90012
Frequently Asked Questions
Yes, both AC & DC coupled systems are allowed. System coupling is up to the developer and site conditions.
The final interconnection cost will be reimbursed, up to $150,000, following the project’s Commercial Operation Date (COD).
There is a minimum 130-day period from the open bidding process to the announcement of awards. Developers will have a 90-day window to submit the application, and we will have a minimum of 40 days to review and analyze the cost of interconnection and annual average price of energy.
Projects that utilize the peak-shaving operation mode may use their battery to supply on-site loads while also participating in FiT+.
Energy used for peak-shaving will not receive any compensation, as it will be serving on-site customer load. We will only provide compensation for energy that is discharged directly to the distribution grid.
We would like to focus 10 MW initially on the 4.8 kV Distribution System and increase the available capacity and expand to the 34.5 kV system based on lessons learned from the 10 MW pilot program. We plan to allocate additional capacity for FiT+ after completion of the pilot.
FiT+ does not allow standalone storage projects. The DER RFP will accommodate standalone batteries. If an existing FiT project is in service or currently has capacity reserved, customers will have an option to retrofit the existing project with energy storage and transition to the FiT+ Program. A new FiT+ Power Purchase Agreement (PPA) will supersede any existing FiT PPAs that have been executed.
There is a 12-month window to bring systems online from the date the agreement is fully executed, with an optional extension provided at our discretion.
An interactive map of the zones is available here. The password can be found in the FiT+ Pilot Program Guidelines.
The program capacity is divided into three tranches with 90-day application submittal windows for each. If there is any remaining capacity in a tranche at the end of the submittal window, the remaining capacity will roll over into subsequent tranche.
Tranche Segmentation |
|||
---|---|---|---|
Tranche | 1st | 2nd | 3rd |
Minimum Available Capacity (MW) |
3 | 3 | 4 |
Bid Submittal Window (calendar days) |
90 | 90 | 90 |
Minimum Review Period (calendar days) |
40 | 40 | 40 |
FiT+ development in the Preferred Zones is prioritized based on CalEnviroScreen scores. We offer priority enrollment for projects located in more impacted areas with higher CalEnviroScreen scores.
If you still have questions, please email [email protected], or call (213) 367-2100.
Questions and Comments
For additional information, please contact us.